[Reader-list] Srinagar Hydro-Electric Project-The Cat is out of Bag
Jeebesh
jeebesh at sarai.net
Tue Aug 18 15:38:41 IST 2009
From Matu People's Organisatioon
matuporg at gmail.com
Project Name: Srinagar Hydro Electric Project 330 MW (but cleared by
MoEF for 200 MW)
River: Bhilangana (Tehri & Pouri Distt.) Uttarakhand
Envionment Clearance: 3-5-1985
Agency: GVK Group of Andhra Pradesh
Srinagar Hydro-Electric Project-The Cat is out of Bag
The Srinagar Hydro Electric Project of 330 MW on the Alaknanda River
in Uttarakhand is a dam that stands on fraud papers, measurements and
accounts. Furthermore, the project is going on paying no heed to
necessary the environmental and legal standards. As a result of this,
the Coffer dam collapsed. The state level and the central level
monitoring is equal to zero and that is the reason why no action is
being taken. It is the phenomenon that has been going on since the
last decade.
On 3rd May 1985, citing the reason of great shortage of electricity in
the region the Centre Govt. gave the Environment Clearance for 200 MW
with some very general conditions. The plan to start the work for the
main dam was in 1987-88 but due to some reasons it did not started.
Till now many project proponent including big names like Tata had
taken the work but left it. At last in 2005 the project is given in
the hands of GVK Group of Andhra Pradesh.
In reffrence to the above, Matu Peoples’ Organisation has written to
various governmental and authorities related to the issue demanding
immediate closure of the construction work so that the environment the
region can be saved. But neither had it got any response nor any
action taken.
The environment clearance for this project was of 200 MW but without
any study or survey it was increased to 330 MW. On the proposal of
Uttar Pradesh State Electricity Board for the environment clearance on
12-3-85, the proposed height of the dam was of 73meters and it was a
run of the river project. In the proposal the authority claimed that
it will not pose negative impact on the environment but it is truly
baseless claims because----
The houses of the affected area have got cracked due to explosive used
for the dam construction.
The muke and other disposles of the dam construction is being thrown
in banks of Alaknanda without making any retaining wall and it is
going in to the river. As a result of it the river changed its way
creating havoc for the colonies of Srinagar town.
Because of the dust due to construction the crops, fodder and
medicinal plants of the region have been harmed.
In the people of the affected area especially in children some
diseases mainly Asthma, Allergy of skin and eyes have increased.
On these very serious issues neither the State Pollution control Board
is paying any heed to it nor is the central agency taking any action
on it.
The conditions those were mentioned in the Environmental Clearance of
29-03-1985 were also not fulfilled.
One of the condition of the Environmental Clearance was that there
should be geo-morphological studies to be undertaken in the catchment
to formulate plans for the stability of the slopes and reservoir
periphery through engineering and biological measures. But in the
Monitoring report of 26-6-06 of the Environment Ministry mentioned
that thus didn’t take place.
If the project authority fulfills the condition of making a 50meter
green belt above the reservoir,they have to acquire any land.for this
purpose. But without the approval of the people, making green belt is
not possible and if the land aqusition is done now then displacement
will be seen as huge. But after the completion of the project the land
can be taken for the purpose by pressurising the people in the name
of security of the dam.
The Central Environment Appraisal Committee has given the clearance
for the 200 MW project on the basis that 300 hectors of land in which
175 hectors of forest land will be submerged. On 12-04-1985 UP Sate
Electricity Board sent a notice to the environment Ministry. Here the
Board had mentioned about the effects of the dam on the environment in
detail, but it was also meant for 200 MW only.
On the basis of that only the Environment Appraisal Committee has
recommended for the environment clearance to the MOEF and the
ministry had given the clearance on 23-3-1985 for 200 MW. The
conditions of the clearance letter were in accordance with the 200 MW
plan.
In September 1986, the Irrigation department of UP decided to increase
the production capacity of Srinagar Power Project from 200 MW to 320.7
MW and sent the proposal to Central Electricity Authority (CEA).
The MOEF and Forest Department of UP had given clearance on the basis
of 338 hector land. On 23-3-90 the Special secretary of UP had written
with detailed conditions to the Forest Dept. of UP to transfer 328.86
hector forest land to the Irrigation Department. The basis of this
letter is also the environmental clearance for 200 MW.
The CEA on 14th June 2000 gave the project re-approval. On 6th of
November 1982 CEA gave financial and technical clearance to the
Srinagar Project as a Run of the River project where as the Ministry
Of Environment and Forest (MOEF) gave approval to it as Run of the
River project with poundage.
According to the rules of 1985, the Environment Clearance from MOEF is
valid for 5 years. But after 14 years in 1999 without any enquiry the
old clearance was extended. The same extension happened after 6 years
again which means that the project is running on the basis of the
clearance of 1985.
In 1985 the proposed height was of 63meters but now it has been
increased to 93 meters. It shows that drastic changes have been made
in the project but on the basis of an age-old environment clearance.
The environment clearance of the dam’s reservoir is of 604 meters but
near Dhari Devi Temple (at the end of the reservior) it touched the
611 meters mark. But the forest clearance was for 605.5 meter reservoir.
The Economic and Technical clearance from CEA was given on 14-06-2000
but the main work of the project is yet to start. The clearance that
was for 3 years got expired on 14-06-2003 but still the work is on?
The CEA in its clearance has clearly mentioned that the cost of the
project is of 1299 crore plus 95 million US dollar. In 2006 MOEF
monitoring committee mentioned cost as 1978 crore. It seems that there
is a big corruption going as the increase of cost of production
effects the cost of power.
In the Onsite Monitoring Report of 26th of August 2008 submitted by
the State Level Committee mentioned that there is no proper hygienic
facility for defection and because of open defection Alaknanda River
and the affected area are getting polluted. To keep the River clean
and from the aspect of environment this is very objectionable and
should be stop immediately. Moreover the details and number of trees
chopped down in the name of dam construction is not available.
In the same report it was ordered to the Pouri office of forest
department to dispose the waste of the project according to a proper
plan from a reputed institute and to do video-graphy of this. But the
Pouri office of the Forest department said that neither their was any
plan nor any video-graphy took place. It was found that no condition
was fulfilled at any stage. It is obvious that the government
departments are not paying any attention to it.
It was planned that in the Srinagar HEP the water will be stored in
the day time and electricity will be produce in the evening at peak
hours. But it will stop the flow of the river. Besides it will
adversely affect the hydro-electric projects at the down of the river
for which the craze is same.
With all these faults and under the table friendship of the government
institutions with the project authorities which is adversely impacting
not only on the Alaknanda River but also on the health and hygiene
of the people of Srinagar and affectd villages. It is also an attack
on the financial and environmental condition of a state and of the
country as a whole. Should these projects still continue even after
that? Only to produce electricity, should we scarifie all the rules,
regulations, environment, our human and natural rights and our moral
values.
Our demand is
Ø The Government should stop this project immediately and release
a white paper.
Ø Proper remuneration and settlement for the displaced.
Ø Find alternatives of Dam work done till now and made arrangment
for the local people so that they can get employment
Vimal bhai
Convenor
Matu Peoples' Organisation
matujan.blogspot.com
Delhi Contact:- D-334/ 10, Ganesh Nagar, Pandav Nagar Complex,
Delhi-110092
91-11-22485545
More information about the reader-list
mailing list